|
|
|
44.
|
A 6,000 sq. ft. bank building is to be constructed and the number of general-purpose receptacles to be installed in the building is yet to be determined; the building will also have an electric sign. Determine the MINIMUM number of 120-volt, 20-ampere branch circuits required for the lighting, receptacles and the sign.
|
|
|
|
|
|
To solve this problem, take into consideration the following:
1) As per Article 100, lighting circuits for a commercial building such as a bank
are considered continuous loads.
2) In compliance with Section 210.19(A)(1), branch-circuits must have an allowable
ampacity of not less than 125% of the continuous loads to be served.
3) General-use receptacles are not considered continuous loads.
4) Electric signs are to be on a separate dedicated circuit. Section 600.5(A)
5) Minimum lighting loads are to be calculated in accordance with the values
given on Table 220.12.
6) As per Section 220.14(K)(2), when the number of receptacles to be installed is
unknown, an additional one (1) VA per sq. ft. is to be added to the general-
lighting load.
Therefore, do the math as shown to determine the minimum number of 120-volt,
20-ampere branch circuits required for this building.
6,000 sq. ft. x 3.5 VA = 21,000 VA x 125% = 26,250 VA (lighting)
6,000 sq. ft. x 1.0 VA = 6,000 VA (receptacles)
32,250 VA (receptacles & lighting)
120 volts x 20 amperes = 2,400 VA of one circuit
32,250 VA (load) 2,400 VA (one circuit) = 13.4 circuits = 14 circuits
14 circuits (lighting & receptacles) + 1 sign circuit = 15 circuits total
Incorrect answer. Please choose another answer.
|
|
|
|
|
To solve this problem, take into consideration the following:
1) As per Article 100, lighting circuits for a commercial building such as a bank
are considered continuous loads.
2) In compliance with Section 210.19(A)(1), branch-circuits must have an allowable
ampacity of not less than 125% of the continuous loads to be served.
3) General-use receptacles are not considered continuous loads.
4) Electric signs are to be on a separate dedicated circuit. Section 600.5(A)
5) Minimum lighting loads are to be calculated in accordance with the values
given on Table 220.12.
6) As per Section 220.14(K)(2), when the number of receptacles to be installed is
unknown, an additional one (1) VA per sq. ft. is to be added to the general-
lighting load.
Therefore, do the math as shown to determine the minimum number of 120-volt,
20-ampere branch circuits required for this building.
6,000 sq. ft. x 3.5 VA = 21,000 VA x 125% = 26,250 VA (lighting)
6,000 sq. ft. x 1.0 VA = 6,000 VA (receptacles)
32,250 VA (receptacles & lighting)
120 volts x 20 amperes = 2,400 VA of one circuit
32,250 VA (load) 2,400 VA (one circuit) = 13.4 circuits = 14 circuits
14 circuits (lighting & receptacles) + 1 sign circuit = 15 circuits total
Incorrect answer. Please choose another answer.
|
|
|
|
|
To solve this problem, take into consideration the following:
1) As per Article 100, lighting circuits for a commercial building such as a bank
are considered continuous loads.
2) In compliance with Section 210.19(A)(1), branch-circuits must have an allowable
ampacity of not less than 125% of the continuous loads to be served.
3) General-use receptacles are not considered continuous loads.
4) Electric signs are to be on a separate dedicated circuit. Section 600.5(A)
5) Minimum lighting loads are to be calculated in accordance with the values
given on Table 220.12.
6) As per Section 220.14(K)(2), when the number of receptacles to be installed is
unknown, an additional one (1) VA per sq. ft. is to be added to the general-
lighting load.
Therefore, do the math as shown to determine the minimum number of 120-volt,
20-ampere branch circuits required for this building.
6,000 sq. ft. x 3.5 VA = 21,000 VA x 125% = 26,250 VA (lighting)
6,000 sq. ft. x 1.0 VA = 6,000 VA (receptacles)
32,250 VA (receptacles & lighting)
120 volts x 20 amperes = 2,400 VA of one circuit
32,250 VA (load) 2,400 VA (one circuit) = 13.4 circuits = 14 circuits
14 circuits (lighting & receptacles) + 1 sign circuit = 15 circuits total
Incorrect answer. Please choose another answer.
|
|
|
|
|
To solve this problem, take into consideration the following:
1) As per Article 100, lighting circuits for a commercial building such as a bank
are considered continuous loads.
2) In compliance with Section 210.19(A)(1), branch-circuits must have an allowable
ampacity of not less than 125% of the continuous loads to be served.
3) General-use receptacles are not considered continuous loads.
4) Electric signs are to be on a separate dedicated circuit. Section 600.5(A)
5) Minimum lighting loads are to be calculated in accordance with the values
given on Table 220.12.
6) As per Section 220.14(K)(2), when the number of receptacles to be installed is
unknown, an additional one (1) VA per sq. ft. is to be added to the general-
lighting load.
Therefore, do the math as shown to determine the minimum number of 120-volt,
20-ampere branch circuits required for this building.
6,000 sq. ft. x 3.5 VA = 21,000 VA x 125% = 26,250 VA (lighting)
6,000 sq. ft. x 1.0 VA = 6,000 VA (receptacles)
32,250 VA (receptacles & lighting)
120 volts x 20 amperes = 2,400 VA of one circuit
32,250 VA (load) 2,400 VA (one circuit) = 13.4 circuits = 14 circuits
14 circuits (lighting & receptacles) + 1 sign circuit = 15 circuits total
Incorrect answer. Please choose another answer.
|